Yes, your installer can set, level and plumb an Ella walk-in tub before your electrical panel work is finished, but the pumps must be powered and run before the walls around the tub are closed. That is because the pre-installation water test is a required one hour check, done before the walls are closed up, and half of it is running every electrical component while you inspect the connections. Plan the upgrade so the dedicated GFCI circuits are live while the tub is still open on every side, and treat the electrical hookup as the last step before finishing, not as something to do after the room is done.
What Connecting the Jets Actually Means
It helps to be clear about what is being postponed. On an Ella tub the jets themselves are never a separate connection. Every therapy system is built into the shell at the factory with its own dedicated pump, plumbing and switches, and the air lines and hydro loop are already in place under the tub when it arrives. The electrical side is simpler than many homeowners expect: the pumps, the in-line heater on hydro packages and the other components run on their rated 3-prong cords, and those cords plug into GFCI protected outlets installed in the compartment behind the access panels. So connecting the jets later really means plugging the pump cords into outlets that your electrician has not installed yet.
Two things follow from that. First, the tub does not need to be rebuilt or modified when the power arrives. The access panels come off, the cords are plugged in, and the panels go back on. Second, waiting on the electrical is not a way to buy a soaker now and add jets later. As the soaking tub conversion article explains, a soaker is molded without jet openings and nothing can be added after it is built. If you want hydro or air massage, the tub has to be ordered as a jetted model, whether or not the circuits are ready on delivery day.
Why the Power Should Be Live Before the Walls Close
The reason not to finish the room and plug the pumps in months later is the leak test. Shipping vibration can loosen unions and air lines, and the water test catches that while every connection is still easy to reach. The required procedure runs in two halves:
- Place the tub on a flat, level surface and confirm leveling, since an unlevel tub can leak at the door during the test.
- Wipe the door seal clean, close the door and tape the drains closed.
- Fill the tub to 3 inches above the highest jet. If the tub has no jets, fill to the bottom of the grab bar.
- Let the water stand for 30 minutes and inspect all around and underneath for any sign of water.
- Run all electrical components, plugged into separate outlets, for another 30 minutes, and inspect all unions and connections again while the pumps run.
The second half is the one that depends on your electrician. Water that sits quietly in a tub does not stress the pump unions or the air lines the way a running blower and hydro pump do, and a leak at a union under pressure is exactly the kind of problem you want to find before tile and drywall cover it. If the tub is set, the walls are finished, and the pumps are first switched on after the upgrade, you have skipped the part of the test that protects you most. Our installation tips video follows the same sequence and goes further, running the air, hydro and electrical components for 20 minutes with a flashlight inspection of every union and suggesting the tub be left filled overnight if the schedule allows.
One safety rule applies at any stage of this plan. Never start a pump until the water covers all the jets. A pump run dry is permanently damaged, and that damage is not covered by the warranty. If the power comes on before the tub is filled for the test, resist the urge to press a button to see the lights come on.
What Your Electrician Must Provide
The upgrade itself has a short list of requirements, and they are the same whether the circuits go in before or after the tub is set. The video on proper electrical requirements shows them: each pump, heater and other component is clearly marked and easily accessible, and your contractor's connection from the tub to your home power supply must use dedicated GFCI protected outlets. The tub cannot share a circuit with any other appliance, the breaker box must also use GFCI protected breakers, and the amperage provided at the panel must match the number and type of components in your tub. The second video covers grounding: every electrical component and the tub frame ship with ground wires, and a proper ground connection must be made following your local and state electrical codes.
How many outlets you need depends on the package. A single therapy needs its own dedicated outlet, and triple packages that combine air, hydro and independent foot massage require two dedicated GFCI 120V 20A outlets, as described in the independent foot massage article. Tell your electrician exactly which package you ordered before the panel work is scoped, so the upgrade covers the right number of circuits the first time.
This step is also the one part of the job that is never optional. Even owners who do the rest of the work themselves must have the GFCI protected circuit provided, installed and tested by a licensed electrician for their area. The self-installation guide spells out the same rule, along with the other conditions that keep your parts warranty and free lifetime technical support in force: level, watertight, nothing cut or modified, and the warranty activation form completed and signed by both the customer and the installer.
A Sequence That Works When the Panel Is Not Ready
If the electrical upgrade cannot happen on the same day as delivery, this order keeps you inside the rules:
- Inspect the tub on delivery and, whenever possible, fill it outside the home to check for transit leaks before it goes in.
- Remove every panel, move the tub in by the frame, and set and level it so every leg carries weight.
- Connect the drain and the water supply. These do not depend on the electrical work.
- Have the electrician complete the dedicated GFCI circuits, the GFCI breakers and the ground connection, with the outlets inside the compartment behind the access panels.
- Run the full pre-installation water test, including the 30 minutes with every component running.
- Only then finish the walls, deck joints and trim around the tub.
The point to agree with your contractor up front is step six. Leaving the surround open until the test is done is a scheduling inconvenience, but it is far cheaper than opening finished walls to reach a loose union. If your contractor needs to confirm anything about the outlets, the package on your order or the test itself, they can open a ticket at ellasbubbles.com/support or call (800) 480-6850 with your model and serial number, and technical support is free for the life of the tub.


Watch: Proper Grounding of Your Walk-In Tub with chapters and a full transcript.
Related Guides
- Electrical requirements by model: dedicated GFCI circuits for your walk-in tub
- What Size Water Heater Do I Need for My Walk-in Tub?
Related Videos

