Support Center / Showers, Panels & Accessories / Installing an Ella One-Piece AcrylX Shower Stall: Alcove Prep, Drain Opening, Fastening and First Use
Back to Showers, Panels & Accessories

Installing an Ella One-Piece AcrylX Shower Stall: Alcove Prep, Drain Opening, Fastening and First Use

Updated September 2026

Installing an Ella one-piece shower stall means setting the AcrylX unit into a framed alcove that matches the rough-in diagram exactly, over a 6 inch floor opening for the 2 inch drain, and fastening it through its nailing flange at every stud and every 8 inches vertically. Because it is one piece, the unit has to be brought into the bathroom before the door framing is finished. This article covers the stall itself; shower kits, bases and the dam are covered in their own articles.

The Unit at a Glance

The current specification manual (dated July 2022) covers the 48 x 37 x 80 inch New Construction One-Piece Shower, model E-3648 LWH or RWH, handed by seat. It is fiberglass reinforced with AcrylX, white, with a 4 inch low threshold and a center drain. Net weight is 160 lbs; it ships in a 53 x 42 x 84 inch crate at 280 lbs. Two packages are listed, Basic and Liberty (the Liberty packages on Ella shower spec sheets are the ones that add stainless steel grab bars), and a 2 inch chrome strainer brass drain with friction seal is included. Every stall has Armorcore reinforced walls so grab bars can be added later without hunting for studs, a Grip Sure textured floor, molded soap, shampoo and foot ledges, and square corners at the base that accept a curtain or a framed or frameless door. Dimensions can vary by plus or minus 1/2 inch. Other one-piece sizes have appeared on earlier spec sheets; ask the team for the current sheet for the exact unit you are considering. The 60 x 33 inch unit with the molded seat is a three-piece shower and has its own installation article; the two are compared in Ella shower stalls compared.

Before You Start

  1. Inspect the unit thoroughly. A damaged unit must never be installed; neither Ella's Bubbles nor the distributor covers removal or reinstallation if a damaged unit goes in. Report transit damage within 48 hours following the freight damage steps.
  2. Get the unit into the bathroom before the door framing is complete, or leave studs out so it can pass.
  3. Check the rough-in dimensions against the job: the alcove must be the size shown on the rough-in diagram, square and plumb, and the floor must be level.
  4. Leave the blocks or legs under the unit in place; they are part of the support system. They do not have to touch the floor for an acceptable install, but if they do not, look for an out-of-level floor. No foundation material is required.
  5. If a fire-rated alcove is required, the approved finish material must be in place before the unit goes in, and the finished alcove must still have the interior dimensions on the diagram.
  6. Provide a 6 inch floor opening for the 2 inch IPS drain connection, located to match the stall's drain position. Keep supply lines and valve plumbing off the studs and out of the alcove, and keep the drain pipe below floor level until the unit is set.
  7. Finish all plumbing to code, cover the unit's floor with cardboard to prevent scuffing, and fasten the drain fitting to the unit before setting it.

Watch: Pocket, Drain and Valve Checks on Video

Step-by-Step Low-Threshold Shower Installation for Remodeling
Chapters in this video
  1. 0:00 Introduction to Low-Threshold Shower Installation This video provides visual guidance for installing a low-threshold 3-piece shower, emphasizing the importance of referring to the installation manual.
  2. 0:24 Dry Assembly and Pre-Installation Checks The installer dry assembles the modular shower to ensure correct panels, drain location, and proper alignment before moving it into the bathroom space.
  3. 1:54 Preparing the Framing Pocket and Subfloor The installer checks the framing pocket for proper sizing, square, plumb, and level, making necessary adjustments and inspecting the subfloor for integrity.
  4. 4:07 Installing the Drain Body and Base Support The installer installs the drain body, prepares the drain to meet local plumbing codes, and applies silicone adhesive for proper support and adhesion of the base.
  5. 5:53 Permanently Installing and Securing the Base The installer permanently positions and levels the shower base, securing it to all available studs and cutting the drain pipe even with the rubber gasket.
  6. 7:22 Installing the Wall Panels and Valve The installer installs the wall panels using a pin and slot system, then installs the valve, connecting the hot and cold water supply lines.
  7. 10:19 Finishing Touches and Accessories The installer caulks all seams, recommends client involvement for accessory placement, and suggests an optional flange trim molding kit for a seamless transition.

This video shows a multi-piece low-threshold shower rather than the one-piece stall, but the parts that matter here are the same: checking the framing pocket for square, plumb and level with a plumb bob, sliding the base into the pocket, marking a threshold line, preparing the 2 inch drain body, and locating the valve and PEX supply before the wet wall closes. Watch it for those checks, then follow the one-piece steps below. Watch: Step-by-Step Low-Threshold Shower Installation for Remodeling with chapters and a full transcript.

Installation Steps

  1. Confirm the framed alcove is the correct size, square and plumb (Diagram 1A in the instructions).
  2. Measure the spout and valve locations from stable reference points such as the back wall studs and floor, and write them down. Mark the fittings on the unit and cut the openings with a fine-tooth or abrasive hole saw, drilling from the smooth inside face outward.
  3. Set the unit into the framing with the drain fitting over the waste pipe and the skirt firmly on the floor. Make sure the waste pipe protrudes well into the drain fitting and the floor keeps its slope toward the drain.
  4. Check for level.
  5. Pre-drill pilot holes and fasten the nailing flange at every stud and every 8 inches vertically. For wood framing use 1 1/2 inch galvanized roofing nails or #10 x 1 1/2 inch self-tapping washer-head screws; for concrete or block, 1 inch concrete nails; for 18 gauge steel studs, drill the flange and stud with a 5/32 inch carbide bit and use #12 x 1 inch sheet metal screws.
  6. Where the finished wall is anything other than cementitious backer board, add furring strips as thick as the nailing flange on the studs above the unit so the walls come out flush. Run 100 percent mildew-resistant silicone between the backer board and the horizontal surface of the unit, then apply the finished wall material.

Clean-Up and First Use

Leave the warranty and maintenance label on the unit for the owner. Remove all debris before the plumbing leak test, using a sponge with warm water and liquid detergent. Never use scouring powders, steel wool, metal scrapers or sandpaper. Plaster and latex paint come off with warm water and a plastic scraper; glues and tars with acetone or paint thinner, never turpentine or lacquer thinner. Dull spots and light scratches buff out with a light-colored automotive rubbing compound.

Care of the AcrylX Surface

  • Clean with warm water and liquid detergent or non-abrasive cleaners made for fiberglass.
  • Apply a good automotive paste wax and buff every six months. Never wax the textured floor.
  • Restore scratches with automotive polishing compound, then re-wax.
  • Remove adhesive with a citrus cleaner, or sparingly with acetone on a white cotton rag, keeping solvents out of the drain and away from pilot lights.
  • Take rubber anti-skid mats out after each use, and wipe up hard water so colors do not fade.

Using cleaners other than those recommended can damage the surface and void the warranty. The wider care routine for stalls, gel coat units and SMC bases is in caring for Ella showers.

Doors and Enclosures

The square corners above the threshold accept a curtain or a framed or frameless door. Ella's Bubbles lists the Duo 55 by 70 framed sliding door for its 60 inch wide stalls, and other sliders in 48 and 60 inch widths; the sizes and adjustment ranges are in glass door and screen options. Never drill into a shower threshold for a door track.

Warranty and Codes

The specification manual lists a Lifetime Limited Residential Warranty and a 30 Year Commercial Warranty for the Ella's Bubbles shower stall. The unit meets UPC, CSA B45.5 and IAPMO Z124 requirements and is manufactured and assembled in the United States. The installation instructions are also published in Spanish and French. The published terms for stalls, doors and seats are gathered in warranty terms for showers, shower doors and accessories.

Common Questions

What rough opening do I frame?
Frame the rough opening to the interior dimensions printed on the rough-in diagram for your specific Ella one-piece shower stall model. The unit will not install correctly in an alcove that is out of square or plumb, so ensure the framing pocket is precisely sized, square, plumb, and level.
Can I set it on a mortar bed?
No, a mortar bed is not required for Ella one-piece shower stalls. These units are supported by integral blocks or legs, which are part of the support system and should remain in place during installation. If the legs do not touch the floor, this indicates an out-of-level floor, and you should address the floor's levelness rather than adding a mortar bed.
Do the grab bars need blocking?
No, grab bars do not need additional blocking in Ella one-piece shower stalls. The Armorcore reinforced walls allow for future grab bars to be added anywhere without needing to locate studs. Grab bars are supplied by others and can be installed later as desired.
Can I add a shower door?
Yes, you can add a shower door to an Ella one-piece shower stall. The square corners above the low threshold are designed to accept either a curtain or a framed or frameless door. For 60-inch wide stalls, Ella's Bubbles lists the Duo 55 by 70 framed sliding door, and other sliders are available in 48 and 60-inch widths; never drill into the shower threshold for a door track. Glass Door and Screen Options Beyond the 4-Fold: Sliding Doors, the Tidy Screen, the LayDown Bi-Fold and the Primo Door
Will the stall fit through my bathroom door?
A one-piece Ella shower stall usually will not fit through a standard bathroom door once the door framing is finished. To ensure the unit can pass, bring it into the bathroom before the door framing is complete, or leave studs out during construction. Will a One-Piece Ella Shower Fit Through My Doorways? The 33-Inch Clearance Rule and New Construction
Which fasteners go through the nailing flange?
The type of fasteners used through the nailing flange depends on your framing material. For wood framing, use 1 1/2 inch galvanized roofing nails or #10 x 1 1/2 inch self-tapping washer-head screws. For concrete or block, use 1 inch concrete nails. For 18 gauge steel studs, you will need to drill the flange and stud with a 5/32 inch carbide bit and use #12 x 1 inch sheet metal screws.
What size is the drain connection?
The drain connection for Ella one-piece shower stalls is a 2 inch IPS drain. You will need to provide a 6 inch floor opening for this connection, ensuring it is located to precisely match the stall's drain position. A 2 inch chrome strainer brass drain with a friction seal is included with the unit.
Where are the installer specs for other one-piece sizes?
Earlier specification sheets for Ella one-piece shower stalls listed other sizes beyond the current 48 x 37 x 80 inch New Construction One-Piece Shower, model E-3648 LWH or RWH. To get the exact installer specifications for a unit you are considering, please ask the Ella's Bubbles team for the current specification sheet.

For anything specific to your unit or configuration, open a ticket at ellasbubbles.com/support.

About this guide. Answers in the Ella’s Bubbles Support Center are compiled from real conversations with tub owners, our technicians’ notes and the product documentation, then reviewed by our team. Tub models and options have evolved over the years, so a detail here may differ slightly from your exact tub. If something looks different on yours, send us your serial number and a specialist will confirm it for your model.

Did this solve your question?

If not, open a ticket and our team will pick it up from here.

Open a Support Ticket